Every permit, who issues it, and what it needs.

This is the full sequence for a service station. The phases run in order, and none of them opens before the one before it closes. In the second phase the filings run in parallel, and each institution wants its own file.

01Previous procedures02Institutional feasibilities03Environmental file04Construction and occupancyEach phase opens the nextMARN resolutionCBESMINECANDAMinistry of HealthAlcaldíaMinistry of LaborUtilityMIDES8 institutions at the same timeThe longest phase6 months from the start orderPhase durations are approximate

Phase by phase

Each card is one filing: the institution that resolves it and what you have to hand in.

01

Previous procedures

First someone has to confirm what you can build on that land, and where it can go.

DOT

Construction line and site qualification

  • Previous-procedures form
  • Copy of the property deed
  • Two signed and sealed copies of the topographic drawing
  • National ID and tax number, or company incorporation papers
DOT

Stormwater feasibility

  • Previous-procedures form
  • Copy of the property deed
  • Two signed and sealed copies of the topographic drawing
  • Legal documentation of the owner
DOT

Road review and zoning

  • Two signed and sealed copies of the architectural plan
  • Area schedule and parking schedule
  • Road profile
  • Bearings and distances schedule
02

Institutional feasibilities

Eight institutions have to approve the project. Each one wants its own paperwork. We file all eight at the same time.

CBES

Fire department resolution

  • Request letter and descriptive memorandum
  • Two signed and sealed copies of the architectural plan
  • Location of signage and extinguishers
  • Road profile and bearings schedule
MINEC

Hydrocarbons resolution

  • Hydrocarbon plan set, signed and sealed
  • Request letter and notarized legal documents
  • Technical brochures for the dispensers
  • Copy of the construction line and the road review
  • Fire department resolution
  • Tabloid location drawing showing adjacent uses
ANDA

Potable water feasibility

  • Topographic drawing
  • Legal documentation
  • Tax clearance
Ministry of Health

Well construction permit

  • ANDA resolution
  • Non-impact study
  • Hydraulic drawing
  • Hydraulic study
  • Only if ANDA denies water and sewerage
Alcaldía

Tree felling, earthworks, solid waste

  • Topographic drawing
  • Municipal tax clearance
  • Legal documents
Ministry of Labor

Workplace risk signage

  • Workplace risk signage drawing
Utility

Electrical service feasibility

  • Legal documentation of the owner
  • Location drawing
MIDES

MIDES letter

  • Common solid waste handling
03

Environmental file

This is the longest part. The MARN reviews the environmental study and decides. Nothing gets built until it says yes.

DOT

Environmental form

  • Filed online with the DOT
DOT / MARN

Environmental Impact Study

  • Air quality study
  • Biological study
  • Social evaluation
  • Hydrological and hydraulic study
  • Complete plan set required for the study
MARN

Public consultation

  • Notice and hearing
  • Response to observations
Imprenta Nacional

Publication in the Diario Oficial

  • Precedes the resolution
MARN

MARN resolution

  • Environmental compliance bond
  • Unlocks the construction permit
04

Construction and occupancy

Once everything else is approved, the construction permit comes through. Then you build, and the last permit lets you open.

DOT

Construction permit

  • Every resolution and feasibility approved
  • Construction plan set
  • Technical studies
DOT

Works acceptance

  • Final inspection
Alcaldía

Occupancy permit

  • Approved works acceptance

Source: permitting process for Estación de Servicio Expres Mart & Gass.

Have a site?

Write with the location and what you want to build. We will tell you which permits it needs and how long they take.